Title: ITEM: AUTHORIZATION TO UTILIZE A CITY OF WEST PALM BEACH CONTRACT AS A BASIS FOR PRICING FOR THE INSTALLATION OF ROCK RIP RAP REQUEST: Authorization to utilize a City of West Palm Beach contract with Murray Logan Construction, LLC. as a basis for pricing for the installation of rock rip rap at 130th Avenue and 50th Street and the southside of 50th Street across 120th Avenue, in the amount of $132,100.00.
Attachments: 1. 1. Quotes Tabulation 7-29-2026, 2. 2. Locations and Standards Combined, 3. 3. Murray Logan Construction - RFQ2026-01 Rock Rip Rap Site 1 and 3 072326, 4. 4. Notice of Intent_Murray Logan_RFQ23.24.405
Date Action ByActionResultVoteMeeting DetailsVideo
No records to display.

…title

ITEM:                     AUTHORIZATION TO UTILIZE A CITY OF WEST PALM BEACH CONTRACT AS A BASIS FOR PRICING FOR THE INSTALLATION OF ROCK RIP RAP

 

REQUEST:                     Authorization to utilize a City of West Palm Beach contract with Murray Logan Construction, LLC. as a basis for pricing for the installation of rock rip rap at 130th Avenue and 50th Street and the southside of 50th Street across 120th Avenue, in the amount of $132,100.00.  

 

…body

EXPLANATION:                     The City of West Palm Beach executed master contracts with various vendors for RFQ 23-24-405.  The Village of Wellington invited all of the awarded vendors to provide a quote for the installation of rock rip rap, at the following locations:  

 

Location 1 is for 130th Avenue and 50th Street and will include furnishing and installing rip rap around an existing culvert pipe where the C-25 ties into the east side of 130th Avenue.

 

Location 2 is for the south side of 50th Street and will include furnishing and installing rock rip rap around the east and west sides of the culvert pipe that connects the C-25 to the C-7 canal.

 

The Village received three (3) quotes utilizing the City of West Palm Beach contract # RFQ 23-24-405 MK, effective through October 9, 2027:

 

Vendors

Location #1: 130th Avenue & 50th Street

Location #2: Southside of 50th Street Across from 120th Avenue

Combined Project Costs 

Murray Logan Construction, LLC

$47,550.00

$84,550.00

$132,100.00

Johnson-Davis Incorporated

$177,365.00

$151,765.00

$329,130.00

FG Construction, LLC

$224,608.00

$305,157.00

$529,765.00

 

Staff recommend utilizing a City of West Palm Beach contract with Murray Logan Construction, LLC. as a basis for pricing for the rock rip rap for 130th Avenue and 50th Street and the south side of 50th Street across 120th Avenue projects, in the amount of $132,100.00.  

 

BUDGET AMENDMENT REQUIRED:                     NO

 

PUBLIC HEARING:                     NO                       QUASI-JUDICIAL:   

 

FIRST READING:                                            SECOND READING:   

 

LEGAL SUFFICIENCY:                     YES

 

FISCAL IMPACT:                     Funding is allocated in the Major Maintenance Account for Surface Water. 

 

WELLINGTON FUNDAMENTAL:                     Protecting our Investment 

 

RECOMMENDATION:                     Authorization to utilize a City of West Palm Beach contract with Murray Logan Construction, LLC. as a basis for pricing for the installation of rock rip rap at 130th Avenue and 50th Street and the southside of 50th Street across 120th Avenue, in the amount of $132,100.00.