File #: 25-7394    Name: AUTHORIZATION TO EXECUTE A TASK ORDER TO HAZEN AND SAWYER TO PROVIDE WATER RECLAMATION FACILITY (WRF) SODIUM HYDROXIDE STORAGE AREA MODIFICATIONS
Type: Purchasing/Contract
Body: Village Council
Agenda Date: 11/12/2025 Final action:
Title: ITEM: AUTHORIZATION TO EXECUTE A TASK ORDER TO HAZEN AND SAWYER TO PROVIDE WATER RECLAMATION FACILITY (WRF) SODIUM HYDROXIDE STORAGE AREA MODIFICATIONS REQUEST: Authorization to execute a Task Order to Hazen and Sawyer to provide Water Reclamation Facility (WRF) Sodium Hydroxide Storage Area Modifications in the amount of $73,223.00.
Attachments: 1. 1. Work Order Proposal - WRF NaOH Storage Area Modifications (002)
Date Action ByActionResultVoteMeeting DetailsVideo
No records to display.

…title

ITEM:                     AUTHORIZATION TO EXECUTE A TASK ORDER TO HAZEN AND SAWYER TO PROVIDE WATER RECLAMATION FACILITY (WRF) SODIUM HYDROXIDE STORAGE AREA MODIFICATIONS

 

REQUEST:                     Authorization to execute a Task Order to Hazen and Sawyer to provide Water Reclamation Facility (WRF) Sodium Hydroxide Storage Area Modifications in the amount of $73,223.00. 

…body

EXPLANATION:                     The Village’s Water Reclamation Facility (WRF) currently utilizes two 3,900-gallon polyethylene bulk sodium hydroxide (NaOH) storage tanks in concrete secondary containment to feed chemical odor control scrubbers throughout the plant. The tanks were installed in 2011 and have reached the end of their useful life. Replacement is necessary to ensure continued safe operation and compliance with current industry standards.

 

This project will develop design and construction documents to replace the existing chemical storage system and related infrastructure to improve safety, functionality, and maintainability.

 

On September 28, 2021, the Village Council awarded RFQ #202121 for Engineering Services to multiple vendors. Hazen & Sawyer, D.P.C. was selected as one of the Village’s water and wastewater treatment engineering consulting service providers. Staff proposes utilizing this existing contract to engage Hazen & Sawyer, who will subcontract with Top Dog Industries LLC to perform professional engineering services for this project.

 

Staff recommends awarding a Task Order to Hazen & Sawyer to provide Water Reclamation Facility (WRF) Sodium Hydroxide Storage Area Modifications in the amount of $73,223.00.

 

BUDGET AMENDMENT REQUIRED:                     NO

 

PUBLIC HEARING:                     NO                      QUASI-JUDICIAL:   

 

FIRST READING:                                            SECOND READING:   

 

LEGAL SUFFICIENCY:                     YES

 

FISCAL IMPACT:                     This project was included in the approved Fiscal Year 2026 Budget.  Funds are available in Utility Capital Plan.  

 

WELLINGTON FUNDAMENTAL:                     Responsive Government  

 

RECOMMENDATION:                     Authorization to execute a Task Order to Hazen and Sawyer to provide Water Reclamation Facility (WRF) Sodium Hydroxide Storage Area Modifications in the amount of $73,223.00.