ITEM: AUTHORIZATION TO AWARD A CONTRACT FOR THE PURCHASE AND DELIVERY OF TWO DIESEL GENERATORS
REQUEST: Authorization to award a contract to Dan Enterprises Team, LLC. for the purchase and delivery of two diesel generators in the amount of $203,547.42.
body
EXPLANATION: The scope of this project is to provide and conduct acceptance testing of two (2) permanent standby electric generating systems at Utility sewer lift stations #16 and #65.
These generators will be purchased as part of the Lift Station Rehabilitation Project. The project includes installing permanent generators on power critical high flow lift stations to ensure system reliability during power losses. Wellington expects to bid the installation portion of the project in early 2024. The purchase of the generators will be fully funded by a $537,232.50 Hazard Mitigation Grant Program grant between the Village of Wellington and the Florida Division of Emergency Management (Agreement H0948).
On, May 1, 2023, Wellington released ITB #202325 (RE-BID) Supply and Delivery of Two Diesel Generators, seeking qualified firms to provide such services. The solicitation was advertised in the Palm Beach Post, the Village’s website, and on DemandStar.com. On June 22, 2023, five (5) proposals were received, as summarized below:
Firm Name |
Price |
American Generator Services LLC |
Non-Responsive |
PERO Engineering and Sales Company, Inc. |
Non-Responsible |
Dan Enterprises Team, LLC |
$203,547.42 |
Zabatt Engine Services, Inc. |
$207,713.00 |
Mid Florida Diesel, Inc. |
$254,202.00 |
American Generator Services, LLC., was deemed non-responsive for not providing the required documentation in their proposal, and PERO Engineering and Sales Company, Inc., was deemed non-responsible for failure to bid the required specifications.
The lowest responsive, responsible bidder was Dan Enterprises Team, LLC, who submitted a bid price of $203,547.42.
Staff is recommending award of contract to Dan Enterprises Team, LLC for the purchase and delivery of two (2) diesel generators in the amount of $203,547.42.
BUDGET AMENDMENT REQUIRED: NO
PUBLIC HEARING: NO QUASI-JUDICIAL:
FIRST READING: SECOND READING:
LEGAL SUFFICIENCY: YES
FISCAL IMPACT: Funds for this project, including the Hazard Mitigation Grant Program funding, are available in the Lift Station Rehab Phase III Capital Project.
WELLINGTON FUNDAMENTAL: Responsive Government
RECOMMENDATION: Authorization to award a contract to Dan Enterprises Team, LLC. for the purchase and delivery of two diesel generators in the amount of $203,547.42.