…title
ITEM: AUTHORIZATION TO AWARD MULTIPLE CONTRACTS FOR UTILITY PROCESS CONTROL ANNUAL MAINTENANCE
REQUEST: Authorization to award contracts to Infamation Technologies Group, LLC dba ITG Technologies, DNA Engineering LLC, and Star Control Inc. for utility process control annual maintenance, at a cost of approximately $104,000 annually.
…body
EXPLANATION: The Utilities Department utilizes a system of Process Logic Computers (PLCs) and a Supervisory Control and Data Acquisition system (SCADA) to operate, monitor, and manage raw water supply wells, the water treatment plant, remote water booster stations, sanitary lift stations, the water reclamation facility and the reuse distribution system. These systems monitor, gather, process real time data, and directly interact with devices such as sensors, valves, pumps and motors. These systems are crucial to maintaining efficiency, processing data for decision-making and communicating system issues to minimize downtime.
On June 27, 2023, the Village released ITB 202330 Utility Process Control Annual Maintenance seeking qualified vendors to provide these services. On July 18, 2023, the Village received four (4) proposals and, for redundancy purposes, the Utilities Department is requesting authorization to award contracts to three (3) firms. The Utilities Department will distribute the work on a project-by-project and emergency basis. The initial term of the contract is for one (1) year from date of award with the option to renew for four (4) additional one (1) year periods.
Firm Name |
Combined Price Per Hour |
Infamation Technologies Group, LLC dba ITG Technologies |
$1,906.00 |
DNA Engineering LLC |
$2,175.00 |
Star Control Inc. |
$2,270.00 |
CC Control Corp |
$3,575.00 |
Staff is seeking authorization to award contracts to Infamation Technologies Group, LLC dba ITG Technologies, DNA Engineering LLC, and Star Control Inc. for utility process control annual maintenance, at a cost of approximately $104,000 annually.
BUDGET AMENDMENT REQUIRED: NO
PUBLIC HEARING: NO QUASI-JUDICIAL:
FIRST READING: SECOND READING:
LEGAL SUFFICIENCY: YES
FISCAL IMPACT: Responsive Government
WELLINGTON FUNDAMENTAL: Funds have been allocated in the FY 23 and FY 24 water treatment facility and water reclamation facility budgets.
RECOMMENDATION: Authorization to award contracts to Infamation Technologies Group, LLC dba ITG Technologies, DNA Engineering LLC, and Star Control Inc. for utility process control annual maintenance, at a cost of approximately $104,000 annually.