ITEM: RATIFICATION OF EMERGENCY WORK PERFORMED TO REPAIR A WATER MAIN FAILURE
REQUEST: Ratification of emergency work performed by Johnson-Davis, Inc. to repair the South Shore Blvd and Vinings Circle water main failure in the amount of $62,500.00.
…body
EXPLANATION: On July 29, 2024, a water valve on the existing 16-inch water main located at South Shore Blvd and Vinings Circle experienced an unforeseen failure. Due to this unforeseen failure and the depth of excavation for the required repair, Utilities staff engaged Johnson-Davis, Inc. to mobilize and provide emergency repair work. Staff utilized a City of Boynton Beach contract as a basis for pricing (Bid No. 019-2521-19/IT Repairs and Emergency Services for Water Distribution, Wastewater Collection, and Storm Water Utility Systems) to complete the repair work. The contract is valid through November 7, 2024.
To date the following invoice has been received for this emergency repair work:
Invoice |
Amount |
Vendor |
Description |
86128 |
$62,500.00 |
Johnson-Davis, Inc. |
Village of Wellington - South Shore Blvd & Vinings Cir Emergency Water Main Repair |
Pursuant to the Purchasing Manual, emergency purchases are exempt from competition in an emergency situation, when the need is the result of a serious and unexpected occurrence and demands immediate action. However, emergency purchases over $50,000 still require Council approval.
Staff is requesting ratification of emergency work performed by Johnson-Davis, Inc. for the South Shore Blvd. and Vinings Circle emergency water main repair in the amount of $62,500.00.
BUDGET AMENDMENT REQUIRED: NO
PUBLIC HEARING: NO QUASI-JUDICIAL:
FIRST READING: SECOND READING:
LEGAL SUFFICIENCY: YES
FISCAL IMPACT: Funds are allocated in the FY 2024 Utilities Operating Budget.
WELLINGTON FUNDAMENTAL: Protecting our Investment
RECOMMENDATION: Ratification of emergency work performed by Johnson-Davis, Inc. to repair the South Shore Blvd and Vinings Circle water main failure in the amount of $62,500.00.