Legislation Details

File #: 26-7519    Name: AUTHORIZATION TO 1) ENTER INTO A SOLE SOURCE CONTINUING CONTRACT FOR WATER TREATMENT PLANT (WTP) STORAGE TANK INSPECTIONS, MAINTENANCE AND UPGRADES AND 2) AUTHORIZATION TO EXECUTE A TASK ORDER FOR FIVE (5) YEAR WATER TREATMENT PLANT (WTP) STORAGE TANK CLE
Type: Purchasing/Contract
Body: Village Council
Agenda Date: 5/12/2026 Final action:
Title: ITEM: AUTHORIZATION TO 1) ENTER INTO A SOLE SOURCE CONTINUING CONTRACT FOR WATER TREATMENT PLANT (WTP) STORAGE TANK INSPECTIONS, MAINTENANCE AND UPGRADES AND 2) AUTHORIZATION TO EXECUTE A TASK ORDER FOR FIVE (5) YEAR WATER TREATMENT PLANT (WTP) STORAGE TANK CLEANING AND INSPECTION SERVICES PROJECT REQUEST: Authorization to 1) Enter into a sole source continuing contract with CROM, LLC DBA CROM Coatings and Restorations for Water Treatment Plant (WTP) Storage Tank Inspections, Maintenance and Upgrades and 2) Authorization to execute a task order for the Five (5) Year Water Treatment Plant (WTP) Storage Tank Cleaning and Inspection Services Project in the amount of $337,935.35.
Attachments: 1. 1. CROM Sole Source Letter 2025, 2. 2. CROM Continuing Contract, 3. 3. CROM - Contract for Task Order 5Yr Storage Tanks
Date Action ByActionResultVoteMeeting DetailsVideo
No records to display.
...title
ITEM: AUTHORIZATION TO 1) ENTER INTO A SOLE SOURCE CONTINUING CONTRACT FOR WATER TREATMENT PLANT (WTP) STORAGE TANK INSPECTIONS, MAINTENANCE AND UPGRADES AND 2) AUTHORIZATION TO EXECUTE A TASK ORDER FOR FIVE (5) YEAR WATER TREATMENT PLANT (WTP) STORAGE TANK CLEANING AND INSPECTION SERVICES PROJECT

REQUEST: Authorization to 1) Enter into a sole source continuing contract with CROM, LLC DBA CROM Coatings and Restorations for Water Treatment Plant (WTP) Storage Tank Inspections, Maintenance and Upgrades and 2) Authorization to execute a task order for the Five (5) Year Water Treatment Plant (WTP) Storage Tank Cleaning and Inspection Services Project in the amount of $337,935.35.

...body
EXPLANATION: CROM is the tank manufacturer and CROM, LLC DBA CROM Coatings and Restorations is the only approved contractor authorized to work on CROM tanks.

Staff is seeking authorization to:

1) Enter into a sole source continuing contract with CROM, LLC DBA CROM Coatings and Restorations for Water Treatment Plant (WTP) Storage Tank Inspections, Maintenance and Upgrades and

2) Authorization to execute a task order for the Five (5) Year Water Treatment Plant (WTP) Storage Tank Cleaning and Inspection Services Project in the amount of $337,935.35 which includes $200,000.00 in owner controlled contingency for any repair work that may be required.

The Utility owns and maintains 6 drinking water storage tanks totaling 8.25 million gallons of daily water storage. The drinking water tanks are generally filled each night and provide the necessary water supply for times of peak flow and fire events. Florida Administrative Code Chapter 62-555.350 requires all drinking water tanks to be taken offline and inspected a minimum of every five (5) years. The scope of the project includes the draining, cleaning, inspection and production of a certified report by a Professional Engineer of all six (6) prestressed, composite ground storage tanks. Each tank's structural integrity...