Skip to main content
Village of Wellington Logo
File #: 25-7084    Name: AUTHORIZATION TO 1) EXECUTE A GUARANTEED MAXIMUM PRICE (GMP) AMENDMENT FOR WELLINGTON TENNIS CENTER EXPANSION AND 2) APPROVE RESOLUTION R2025-43 AMENDING THE FISCAL YEAR 2024-2025 RECREATION IMPACT CAPITAL FUND BUDGET AND REASSIGNING RECREATION IMPACT RES
Type: Purchasing/Contract
Body: Village Council
Agenda Date: 6/10/2025 Final action:
Title: ITEM: AUTHORIZATION TO 1) EXECUTE A GUARANTEED MAXIMUM PRICE (GMP) AMENDMENT FOR WELLINGTON TENNIS CENTER EXPANSION PROJECT AND 2) APPROVE RESOLUTION R2025-43 AMENDING THE FISCAL YEAR 2024-2025 RECREATION IMPACT CAPITAL FUND BUDGET AND ASSIGNING RECREATION IMPACT RESERVES FOR THE TENNIS CENTER EXPANSION PROJECT REQUEST: 1) Authorization to execute a Guaranteed Maximum Price (GMP) Amendment with Burkhardt Construction, Inc. for Wellington Tennis Center Expansion Project in the amount of $2,050,00 and 2) Approve Resolution R2025-43 amending the Fiscal Year 2024-2025 Recreation Impact Capital Fund Budget and assigning Recreation Impact Reserves for the Tennis Center Expansion Project.
Attachments: 1. 1. BA Resolution No. R2025-43 Tennis Center Contract $650,000 Rec Impact, 2. 2. DRAFT - GMP Burkhardt Tennis Center Expansion -
Date Action ByActionResultVoteMeeting DetailsVideo
No records to display.
...title
ITEM: AUTHORIZATION TO 1) EXECUTE A GUARANTEED MAXIMUM PRICE (GMP) AMENDMENT FOR WELLINGTON TENNIS CENTER EXPANSION PROJECT AND 2) APPROVE RESOLUTION R2025-43 AMENDING THE FISCAL YEAR 2024-2025 RECREATION IMPACT CAPITAL FUND BUDGET AND ASSIGNING RECREATION IMPACT RESERVES FOR THE TENNIS CENTER EXPANSION PROJECT

REQUEST: 1) Authorization to execute a Guaranteed Maximum Price (GMP) Amendment with Burkhardt Construction, Inc. for Wellington Tennis Center Expansion Project in the amount of $2,050,00 and 2) Approve Resolution R2025-43 amending the Fiscal Year 2024-2025 Recreation Impact Capital Fund Budget and assigning Recreation Impact Reserves for the Tennis Center Expansion Project.

...body
EXPLANATION: Pursuant to RFQ# 202010, on May 12, 2020, the Village Council awarded a continuing Construction Manager at Risk (CMAR) contract to Burkhardt Construction, Inc.

Staff is seeing authorization to execute a Guaranteed Maximum Price (GMP) Amendment for the Wellington Tennis Center Expansion Project in the amount of $2,050,000. The scope of work includes the addition of three (3) hard tennis courts, three (3) clay tennis courts, a 19' X 9' shade canopy and additional lighting.

This expansion is being proposed in response to increased demand and growing community interest in tennis programming and court availability.

The cost of the project is $2,050,000 which includes an owner-controlled contingency in the amount of $134,116.30.

Staff recommends executing a Guaranteed Maximum Price (GMP) Amendment in the amount of $2,050,00 and 2) Approving Resolution R2025-43 amending the fiscal year 2024-2025 Recreation Impact Capital Fund Budget and Assigning Recreation Impact Reserves for the Tennis Center Expansion Project.

BUDGET AMENDMENT REQUIRED: YES

PUBLIC HEARING: QUASI-JUDICIAL:

FIRST READING: SECOND READING:

LEGAL SUFFICIENCY: YES

FISCAL IMPACT: The attached budget amendment will assign an additional $650,000 from Recreation Impact...

Click here for full text