ITEM: APPROVAL OF ADDITIONAL WORK REQUIRED FOR THE GYM ROOF REPLACEMENT PROJECT AT VILLAGE PARK
REQUEST: Approval of additional work required for the gym roof replacement at Village Park, in the amount of $27,699.65.
…body
EXPLANATION: On June 24, 2025, Council awarded a contract to Weather Guard Industries/SMJ Metals, LLC. for the roof replacement project at Village Park, in the amount of $113,693.19. Due to unforeseen additional work, an additional $27,699.65 is needed to complete the project. The cost includes the procurement of plywood by Wellington and installation by Weather Guard Industries/SMJ Metals, LLC. The plywood will be attached to the existing metal decking per the calculations provided by the consultant.
Pursuant to the Village’s Purchasing Manual, the change order threshold for this procurement requires Council approval. Total expenditures that will be paid upon completion of this project will be $141,392.84.
Staff is requesting approval of the cost for the additional work needed to complete this project.
BUDGET AMENDMENT REQUIRED: NO
PUBLIC HEARING: NO QUASI-JUDICIAL:
FIRST READING: SECOND READING:
LEGAL SUFFICIENCY: YES
FISCAL IMPACT: Funds for this project is allocated in Building Maintenance Major Maintenance Fund account.
WELLINGTON FUNDAMENTAL: Responsive Government
RECOMMENDATION: Approval of additional work required for the gym roof replacement at Village Park, in the amount of $27,699.65.