ITEM: AUTHORIZATION TO AWARD CONTRACTS FOR THE 40TH STREET WATERMAIN PROJECT AND RESOLUTION NO. R2016-74 WHICH AMENDS THE FISCAL YEAR 2017 BUDGET AND APPRORIATES THE FUNDS FOR PROJECT EXPENSE
A RESOLUTION OF WELLINGTON, FLORIDA'S COUNCIL AMENDING THE WATER AND WASTEWATER FUND MAJOR MAINTENANCE BUDGET FOR FISCAL YEAR 2016-2017 BY ALLOCATING FUND BALANCE TO THE 40th STREET WATER MAIN REPLACEMENT PROJECT; AND PROVIDING AN EFFECTIVE DATE.
REQUEST: Authorization to award contracts to multiple vendors for the 40th Street Watermain project, as summarized below, and to approve Resolution No. R2016-74 which amends the Fiscal Year 2017 Budget and appropriates the funds for project expense and ratifies the related emergency procurement purchase order issued October 26, 2016.
...body
EXPLANATION: The 40th Street Watermain Project (Project) is located within the 40th Street right-of-way (Exhibit A - Location Map). The Project includes the removal and disposal of 6,000 feet of 12" ductile iron watermain due to the presence of muck under/ adjacent to the existing pipeline. The existing watermain is located below the proposed centerline of the new roadway. A new replacement watermain consisting of 4,500 ft of 8" pipe and 1,600 feet of 12"pipe, will be constructed below the south edge of the new pavement. The costs associated with this project are summarized below:
Vendor
Description Of Services
Amount
1. Fortiline Waterworks
1600ft of 12" Pipe
$46,960.00
2. Ferguson Waterworks
Fittings
$11,094.46
3. The Eddie Huggins
Land Grading Co., LLC
Remove and dispose of existing watermain, muck removal and clean fill.
Not to Exceed - $140,000
4. Johnson Davis, Inc.
40th Street Watermain Replacement - Pipeline Construction
$267,769.85
The Project must be completed concurrently with the construction of 40th Street so as not to delay the new roadway construction. The roadway construction is being built by Wellington Equestrian Partners as a condition of approval of the ...