...title
ITEM: AUTHORIZATION TO AWARD A CONTRACT FOR WELLINGTON WETLAND PARK BOARDWALK REFURBISHMENT (PHASE 1)
REQUEST: Authorization to award a contract to Interstate Construction, LLC, for the Wellington Wetland Park Boardwalk Refurbishment (Phase 1) in the amount of $149,236.00.
...body
EXPLANATION: The Peaceful Water Wetlands requires replacement of the wood decking. The Utility Department has established a three-phase approach over three (3) years to replace the wooden boardwalk. The new material will be an engineered planking that has a useful life of approximately twenty (20) years. Phase one of the project includes removal and replacement of approximately 196' of wood framed boardwalk super structure and railing. This project will also include the removal and replacement of approximately 85' of wood framed railing on existing concrete sidewalk.
On February 28, 2018, Wellington released ITB #008-18/MM on Demandstar, seeking qualified firms to provide such services. The solicitation was also advertised in the Palm Beach Post and posted on Wellington's website. On March 26, 2018, three (3) proposals were received.
Vendor
Amount
Local Vendor Status
Interstate Construction, LLC
$149,236.00
Not Local
Underwater Engineering Services, Inc.
$162,821.44
Not Local
J. Rawn Enterprises, Inc.
$188,734.00
Western Communities
Staff is recommending award of contract to Interstate Construction, LLC, the lowest responsive, responsible bidder, for the Wellington Wetland Park Boardwalk Refurbishment (Phase 1) in the amount of $149,236.00.
BUDGET AMENDMENT REQUIRED: NO
PUBLIC HEARING: NO QUASI-JUDICIAL:
FIRST READING: SECOND READING:
LEGAL SUFFICIENCY: YES
FISCAL IMPACT: Funds for this project are available in the Peaceful Waters Wetland Capital Project 401-7050-536.65-11 Project 201852.
WELLINGTON FUNDAMENTAL: Responsive Government
RECOMMENDATION: Authorization to award a contract to Interstate Construction, LLC, for the Wellington Wetlan...