File #: 14-1039    Name: AUTHORIZATION TO AWARD A CONTRACT FOR THE PIERSON ROAD SIDEWALK IMPROVEMENTS
Type: Purchasing/Contract
Body: Village Council
Agenda Date: 2/10/2015 Final action: 2/1/2016
Title: ITEM: AUTHORIZATION TO AWARD A CONTRACT FOR THE PIERSON ROAD SIDEWALK EXTENSION PROJECT REQUEST: Authorization to award a contract to Wynn & Son Environmental Construction Co., Inc. for the sidewalk improvements on Pierson Road in the amount of $143,000.00.
Attachments: 1. 1. Wynn Submittal, 2. 2. Bid Tabulation, 3. 3. Notice of Intent, 4. 4. Plans
...title
ITEM: AUTHORIZATION TO AWARD A CONTRACT FOR THE PIERSON ROAD SIDEWALK EXTENSION PROJECT

REQUEST: Authorization to award a contract to Wynn & Son Environmental Construction Co., Inc. for the sidewalk improvements on Pierson Road in the amount of $143,000.00.

...body
EXPLANATION: This project provides for a sidewalk along Pierson Road between 120th Ave. and the entrance to Village Park. The new sidewalk will be 6 ft. wide and will be constructed along the south side of Pierson Road. This project is part of Wellington's approved 2015 Capital Improvement Plan. Plans for the project are included as Attachment #4.

On December 22, 2014, Wellington released ITB #034-14/DZ on Demandstar. The solicitation was also advertised in the Palm Beach Post and posted on Wellington's website. On January 14, 2014, five (5) proposals were received.

Vendor
Bid Amount
Local Vendor Status
Wynn & Sons Environmental Co, Inc.
$144,366.00
Palm Beach County
All-Site Construction, Inc.
$178,286.66
Palm Beach County
West Construction, Inc.
$197,075.20
Palm Beach County
Rosso Site Development, Inc.
$205,121.55
Palm Beach County
Lambert Bros., Inc.
$214,639.10
Not Local

Staff is recommending award of contract to Wynn & Son Environmental Construction Co., Inc., the lowest responsive, responsible bidder for the sidewalk improvements on Pierson Road in the amount of $144,366.00, including a $16,358 owner controlled contingency. The amount budgeted for this project is $143,000, approximately $1,366 (0.95%) lower than the bid amount. Staff recommends awarding the contract to Wynn and Son Environmental Co., Inc. in the amount of $143,000.

BUDGET AMENDMENT REQUIRED: NO

PUBLIC HEARING: NO QUASI-JUDICIAL:

FIRST READING: SECOND READING:

LEGAL SUFFICIENCY: YES

FISCAL IMPACT: Funds for this project are available in the Pierson Sidewalk Extension Capital Project - Acct. #133-2021-541.65-71.

WELLINGTON FUNDAMENTAL: Responsive Government
...