File #: 17-0835    Name: AUTHORIZATION TO AWARD A CONTRACT FOR THE PURCHASE AND INSTALLATION OF VARIABLE FREQUENCY DRIVES FOR PUMP STATIONS 3, 6, AND 7
Type: Purchasing/Contract
Body: Village Council
Agenda Date: 3/28/2017 Final action:
Title: ITEM: AUTHORIZATION TO AWARD A CONTRACT FOR THE PURCHASE AND INSTALLATION OF VARIABLE FREQUENCY DRIVES FOR PUMP STATIONS 3, 6, AND 7 REQUEST: Authorization to award a contract to Grid One Electrical Construction, Inc., for the purchase and installation of variable frequency drives (VFDs) for pump stations 3, 6 and 7 in the amount of $196,626.00.
Attachments: 1. 1. Bid Tabulation, 2. 2. Notice of Intent, 3. 3. Hyperlink to Bid Documents
Date Action ByActionResultVoteMeeting DetailsVideo
No records to display.

…title

ITEM:  AUTHORIZATION TO AWARD A CONTRACT FOR THE PURCHASE AND INSTALLATION OF VARIABLE FREQUENCY DRIVES FOR PUMP STATIONS 3, 6, AND 7 

 

REQUEST:  Authorization to award a contract to Grid One Electrical Construction, Inc., for the purchase and installation of variable frequency drives (VFDs) for pump stations 3, 6 and 7 in the amount of $196,626.00. 

 

…body

EXPLANATION:  The Public Works Department is seeking authorization to award a contract for the purchase and installation of variable frequency drives for pump stations 3, 6 and 7. This purchase will enhance the Village’s ability to pump storm water to the C-51 Canal prior to and after a storm event. The new VFDs will allow the Village to continue to pump by adjusting the speed of the pump by raising or lowering the frequency and voltage of the electricity supplied to the electric motor without damaging the pump motor.

 

On January 22, 2017, Wellington released ITB #002-17/DZ on Demandstar. The solicitation was also advertised in the Palm Beach Post and posted on Wellington’s website. On February 15, 2017, two (2) proposals were received.

 

Vendor

Amount

Local Vendor Status

Grid One Electrical Construction, Inc.

$196,626.00

Western Communities

Flanders Electric Motor Service

Non Responsive

Not Local

 

Grid One Electrical Construction, Inc. submitted the lowest, responsive, responsible bid of $196,626.00. The second bidder, Flanders Electric Motor, was not properly licensed to bid or contract such work, and was therefore deemed non-responsive.

 

Staff recommends authorization to award a contract to Grid One Electrical Construction, Inc., for the purchase and installation of variable frequency drives for pump stations 3, 6 and 7 in the amount of $196,626.00.

 

All related bid documents can be found by clicking on the following link:

<http://www.wellingtonfl.gov/Home/Components/RFP/RFP/277/203> 

 

BUDGET AMENDMENT REQUIRED:                     NO 

 

PUBLIC HEARING:                     NO                       QUASI-JUDICIAL:                      

 

FIRST READING:                                            SECOND READING:                      

 

LEGAL SUFFICIENCY:                     YES 

 

FISCAL IMPACT:                     Funds for the project are available in SWM System Rehabilitation Capital Project budget.

 

WELLINGTON FUNDAMENTAL:                     Responsive Government 

 

RECOMMENDATION:                     Authorization to award a contract to Grid One Electrical Construction, Inc., for the purchase and installation of variable frequency drives for pump stations 3, 6 and 7 in the amount of $196,626.00.