File #: 18-2168    Name: AUTHORIZATION TO AWARD A TASK ORDER TO PROVIDE ENGINEERING CONSULTING SERVICES FOR THE FOREST HILL BOULEVARD/C-8 CANAL IMPROVEMENT PROJECT
Type: Purchasing/Contract
Body: Village Council
Agenda Date: 7/10/2018 Final action:
Title: ITEM: AUTHORIZATION TO AWARD A TASK ORDER TO PROVIDE ENGINEERING CONSULTING SERVICES FOR THE FOREST HILL BOULEVARD/C-8 CANAL IMPROVEMENT PROJECT REQUEST: Authorization to award a task order to Mock Roos and Associates, Inc. to provide additional engineering design services for the Forest Hill Boulevard/C-8 Canal Improvement Project at a cost of $38,058.00.
Attachments: 1. 1. Mock Roos Proposal
Date Action ByActionResultVoteMeeting DetailsVideo
No records to display.
...title
ITEM: AUTHORIZATION TO AWARD A TASK ORDER TO PROVIDE ENGINEERING CONSULTING SERVICES FOR THE FOREST HILL BOULEVARD/C-8 CANAL IMPROVEMENT PROJECT

REQUEST: Authorization to award a task order to Mock Roos and Associates, Inc. to provide additional engineering design services for the Forest Hill Boulevard/C-8 Canal Improvement Project at a cost of $38,058.00.

...body
EXPLANATION: On February 21, 2018, the Village released ITB#006-18/DZ seeking qualified contractors for the Forest Hill Boulevard/C-8 Canal improvement project. On March 28, 2018, we received four (4) bids that met the minimum requirements of the solicitation.

The total budget for this project was $2.2 million or $337,648.60 less than the low bid. In an effort to reduce costs, on May 15, 2018, the Village rejected all bids. It is our intent to re-bid the project and include lower cost installation options. Mock Roos did the original design and this task order authorizes the engineering required for the installation options

The original design included micro-tunneling a new pipe under Forest Hill Boulevard. The new bid documents will include an alternate to open-cut, remove and replace the culverts within the Forest Hill Boulevard/C-8 Canal right of ways.

Staff recommends awarding a task order to Mock Roos and Associates, Inc. to provide the engineering services required for alternate installation options at a cost of $38,058.00.

BUDGET AMENDMENT REQUIRED: NO

PUBLIC HEARING: NO QUASI-JUDICIAL:

FIRST READING: SECOND READING:

LEGAL SUFFICIENCY: YES

FISCAL IMPACT: Funds for this project are available in the Forest Hill Boulevard and C-8 Canal Improvements capital project (301-2010-538.65-68 Project 201856).

WELLINGTON FUNDAMENTAL: Responsive Government

RECOMMENDATION: Authorization to award a task order to Mock Roos and Associates, Inc. to provide additional engineering design services for the Forest Hill Boulevard/C-8 Canal Improvement Project at a cost ...