File #: 19-2765    Name: AUTHORIZATION TO AWARD A CONTRACT FOR THE VILLAGE PARK CONCESSION STAND DOOR REPLACEMENT - PHASE II PROJECT
Type: Purchasing/Contract
Body: Village Council
Agenda Date: 4/23/2019 Final action:
Title: ITEM: AUTHORIZATION TO AWARD A CONTRACT FOR THE VILLAGE PARK CONCESSION STAND DOOR REPLACEMENT - PHASE II PROJECT REQUEST: Authorization to award a contract to CJ Contracting, LLC, for the Village Park Concession Stand Door Replacement - Phase II project, in the amount of $105,205.00.
Attachments: 1. 1. Bid Tabulation & Checklist, 2. 2. Notice of Intent, 3. 3. SOCCER #1 FIELD-PLANS, 4. 4. SOCCER #2 FIELD-PLANS, 5. 5. LACROSSE FIELD-PLANS, 6. 6. CJ CONTRACTING, LLC. PROPOSAL
Date Action ByActionResultVoteMeeting DetailsVideo
No records to display.

…title

ITEM:                     AUTHORIZATION TO AWARD A CONTRACT FOR THE VILLAGE PARK CONCESSION STAND DOOR REPLACEMENT - PHASE II PROJECT 

 

REQUEST:                     Authorization to award a contract to CJ Contracting, LLC, for the Village Park Concession Stand Door Replacement - Phase II project, in the amount of $105,205.00.

 

…body

EXPLANATION:                     This project includes removal and replacement of existing concession stand doors at Village Park Soccer Field #1; Village Park Soccer Field #2; and Village Park Lacrosse Field. The buildings are between 15 and 20 years old and as such, the existing metal doors and frames have deteriorated, and thus require replacement.  The existing metal doors will be replaced by fiberglass doors.

 

On March 11, 2019, Wellington released ITB 201907 seeking qualified firms to provide such services. On April 2, 2019, the Village received three (3) proposals as summarized below:

 

Vendor

Amount

Local Vendor Status

CJ Contracting, LLC.

$105,205.00

Western Communities

Close Construction, LLC.

$116,361.00

Non-Local

Creative Contracting, Group

$118,600.00

Western Communities

 

Staff recommends awarding a contract to CJ Contracting, LLC. the lowest responsive, responsible bidder for the Village Park Concession Stand Door Replacement - Phase II project, in the amount of $105,205.00. The contractor has indicated they would be performing the work in house and will not necessitate the use of subcontractors.

 

BUDGET AMENDMENT REQUIRED:                     NO 

 

PUBLIC HEARING:                     NO                       QUASI-JUDICIAL:                      

 

FIRST READING:                                            SECOND READING:                      

 

LEGAL SUFFICIENCY:                     YES

 

FISCAL IMPACT:                     Funds for this project are available in the Village Park Capital Project (CPW18029). The project is part of the approved one cent sales surtax funded projects.

 

WELLINGTON FUNDAMENTAL:                     Responsive Government

 

RECOMMENDATION:                     Authorization to award a contract to CJ Contracting, LLC, for the Village Park Concession Stand Door Replacement - Phase II project, in the amount of $105,205.00.