Title: ITEM: AUTHORIZATION TO UTILIZE AN EXISTING PUBLIC WORKS ANNUAL CONTRACT TO REPLACE/ADD CULVERTS REQUEST: Authorization to utilize an annual public works contract with D.S. Eakins Construction Corporation for the replacement/addition of culverts, at a cost of $136,110.00.
Attachments: 1. 1. Proposal #1-150th Ave S & 40th Ave S, 2. 2. Plans-Proposal #1, 3. 3. Proposal #2-Ousley Farms Rd, 4. 4. Plans-Proposal #2, 5. 5. C2 and C24D Improvements Map - Plan
Date Action ByActionResultVoteMeeting DetailsVideo
No records to display.
...title
ITEM: AUTHORIZATION TO UTILIZE AN EXISTING PUBLIC WORKS ANNUAL CONTRACT TO REPLACE/ADD CULVERTS

REQUEST: Authorization to utilize an annual public works contract with D.S. Eakins Construction Corporation for the replacement/addition of culverts, at a cost of $136,110.00.

...body
EXPLANATION: The Public Works Department is seeking authorization to utilize an annual Public Works contract (007-15/DZ), previously approved by Council on July 14, 2015, with D.S. Eakins for the following culvert replacement/addition:

1). Location #1: Replace the existing 72" culvert on the C2 Canal Bridle Crossing just south of the C24 Canal with Twin 84" Corrugated Aluminum Pipe (CAP) culverts. The increase pipe diameter and additional pipe will relieve the choke point and increase the flow from Storm Water Basin B to Storm Water Basin A during major storm events.

2). Location #2: Install a new 72" CAP culvert under Ousley Farms Rd to make the connection between the C2 and C24D Canals. The additional connection to the C2 Canal will provide a secondary outfall for this area and will increase the flow from Storm Water Basin B to Storm Water Basin A during major storm events.

Staff is seeking authorization to utilize D.S. Eakins Construction Corporation, under their existing approved contract for Location #1 at cost of $74,550.00 and Location #2 at a cost of $61,560.00 for a total combined project cost of $136,110.00. Public Works will be supplying the pipe material and D.S. Eakins Construction Corporation will be installing the pipes utilizing the existing contract.

BUDGET AMENDMENT REQUIRED: NO

PUBLIC HEARING: NO QUASI-JUDICIAL:

FIRST READING: SECOND READING:

LEGAL SUFFICIENCY: YES

FISCAL IMPACT: Funds for these projects are budgeted in the 2014 Acme & Replacement Program Capital Improvement Budget.

WELLINGTON FUNDAMENTAL: Responsive Government

RECOMMENDATION: Authorization to utilize an annual public works contract with D.S. Eakins Construction ...