File #: 19-3394    Name: AUTHORIZATION TO AWARD A TASK ORDER TO PROVIDE CONSULTING SERVICES FOR THE WATER RECLAMATION FACILITY DEVELOPMENT OF PROCESS AND INSTRUMENTATION DIAGRAMS
Type: Purchasing/Contract
Body: Village Council
Agenda Date: 12/10/2019 Final action:
Title: ITEM: AUTHORIZATION TO AWARD A TASK ORDER TO PROVIDE CONSULTING SERVICES FOR THE WATER RECLAMATION FACILITY DEVELOPMENT OF PROCESS AND INSTRUMENTATION DIAGRAMS REQUEST: Authorization to approve a task order to Hazen and Sawyer, P.C. to provide engineering services for the Water Reclamation Facility Development of Process and Instrumentation Diagrams at a cost of $140,308.00.
Attachments: 1. 1. Work Order 20 - P&IDs FINAL
Date Action ByActionResultVoteMeeting DetailsVideo
No records to display.
...title
ITEM: AUTHORIZATION TO AWARD A TASK ORDER TO PROVIDE CONSULTING SERVICES FOR THE WATER RECLAMATION FACILITY DEVELOPMENT OF PROCESS AND INSTRUMENTATION DIAGRAMS

REQUEST: Authorization to approve a task order to Hazen and Sawyer, P.C. to provide engineering services for the Water Reclamation Facility Development of Process and Instrumentation Diagrams at a cost of $140,308.00.

...body
EXPLANATION: On August 8, 2017, Council awarded an engineering contract (004-17/DZ) to multiple vendors. As part of the solicitation, Hazen and Sawyer, P.C. was selected as one of the Village's engineering service providers. Staff is seeking authorization to utilize such contract with Hazen and Sawyer, P.C. to provide engineering consulting services for the Water Reclamation Facility Development of Process and Instrumentation Diagrams for the Village of Wellington.

The Village of Wellington Water Reclamation Facility is currently under construction for a $19 Million renewal and replacement and expansion project. Additionally, a separate construction project will replace existing Process Logic Controllers (PLCs) which have exceeded their useful life. These PLCs control all aspects of plant operations. In order to bid the PLC replacement project and document improvements under the ongoing construction project, development of Process and Instrumentation Diagrams (PIDs) are required. The PIDs are essential for the Utility and outside contractors to troubleshoot and modify the plant control systems. The project is anticipated to be completed within nine months of approval. Funding for this project is in the approved Utility Capital Budget.

Staff recommends a task order to Hazen and Sawyer, P.C. to provide engineering consulting services for the Water Reclamation Facility Development of Process and Instrumentation Diagrams at a cost of $140,308.00.

BUDGET AMENDMENT REQUIRED: NO

PUBLIC HEARING: NO QUASI-JUDICIAL:

FIRST READING: SECOND READING:

LEGAL SUFFICIENCY: ...