File #: 21-4637    Name: AUTHORIZATION TO UTILIZE EXISTING CONTRACTS AND AWARD SOLE SOURCE CONTRACTS FOR VARIOUS FY 2022 PUBLIC WORKS PROJECTS
Type: Purchasing/Contract
Body: Village Council
Agenda Date: 10/12/2021 Final action:
Title: ITEM: AUTHORIZATION TO UTILIZE EXISTING CONTRACTS AND AWARD SOLE SOURCE CONTRACTS FOR VARIOUS FY 2022 PUBLIC WORKS PROJECTS REQUEST: Authorization to utilize existing contracts and award sole source contracts for various FY 2022 Public Works Projects with a budgeted total amount of $3,390,000.00.
Attachments: 1. 1. Amesbury Circle Subdivision Map, 2. 2. Chancellor Drive Map, 3. 3. Greenview Shores I Map, 4. 4. Paddock Park Map, 5. 5. Westhampton Subdivision Map, 6. 6. Aero Club Drive Map, 7. 7. Forest Hill Boulevard Map, 8. 8. Stribling Pathway Map, 9. 9. Pierson Road Guardrail Maps, 10. 9A. Ousley Farms Road Guardrail Map, 11. 10. Surface Water - Desilting Map C2-C27A, 12. 10. Surface Water - Desilting Map C-2 to C-24, 13. 11. Surface Water - Drainage Pipe Lining and Culvert Inspection Maps, 14. 12. MWI Sole Source Letter, 15. 13. MWI Pumps Quote, 16. 14. Hydro Component Systems, LLC
Date Action ByActionResultVoteMeeting DetailsVideo
No records to display.

…title

ITEM: AUTHORIZATION TO UTILIZE EXISTING CONTRACTS AND AWARD SOLE SOURCE CONTRACTS FOR VARIOUS FY 2022 PUBLIC WORKS PROJECTS 

 

REQUEST: Authorization to utilize existing contracts and award sole source contracts for various FY 2022 Public Works Projects with a budgeted total amount of $3,390,000.00.  

…body

EXPLANATION: The Public Works Department is seeking authorization to utilize existing contracts and award sole source contracts for various FY 2022 exceeding the Village’s $50,000 threshold.

 

The projects include: 1) Roadway milling, resurfacing, traffic striping, valley gutter, guardrail installation and sidewalk maintenance 2) Swale maintenance and reconstruction, sod installation, canal desilting, drainage pipe cleaning and lining, culvert inspection 3) Pump Station 4 water lube conversion 4) Reconditioning trash rake at pump station 7. 

 

Contracts to be utilized and projects are summarized below:    

 

Roads:

Project Location

Description

Contracts

Amesbury Circle Subdivision

Thermo striping, riser rings, milling, asphalt and valley gutters.

VOW ITB #202028 - Asphalt Milling expires 10/26/23 VOW ITB #006-17/ENR - Roadway Striping expires 5/9/22 VOW ITB #202112 - Minor Construction expires 5/10/24 PBC Contract #2020055 - Pathway & Minor Construction expires 11/16/23

Chancellor Drive From South Shore Boulevard to Ken Adams Way

Mill and resurface

VOW ITB #202028 - Asphalt Milling expires 10/26/23

Greenview Shores I

Overbuild, thermos striping, riser rings, milling, and asphalt

VOW ITB #202028 - Asphalt Milling expires 10/26/23 VOW ITB #006-17/ENR - Roadway Striping expires 5/9/22

Paddock Park

Thermo striping, milling and asphalt.

VOW ITB #202028 - Asphalt Milling expires 10/26/23 VOW ITB #006-17/ENR - Roadway Striping expires 5/9/22

 

 

Project Location Description Contracts

 

 

Westhampton Subdivision

Concrete work, valley gutters, thermos striping, riser rings, milling and asphalt

VOW ITB #202028 - Asphalt Milling expires 10/26/23 VOW ITB #006-17/ENR - Roadway Striping expires 5/9/22 VOW ITB #202112 - Minor Construction expires 5/10/24 PBC Contract #2020055 - Pathway & Minor Construction expires 11/16/23

Aero Club Drive - From Greenview Shores intersection to Greenbriar Boulevard

Reinstall traffic signal loops, thermo striping, milling and asphalt

VOW ITB #202028 - Asphalt Milling expires 10/26/23 VOW ITB #006-17/ENR - Roadway Striping expires 5/9/22 PBC Traffic Engineering - Signal Loops

Forest Hill Boulevard - From Wellington Trace at Town Center to Birkdale Drive

Reinstall traffic signal loops, thermo striping, milling and asphalt.

VOW ITB #202028 - Asphalt Milling expires 10/26/23 VOW ITB #006-17/ENR - Roadway Striping expires 5/9/22 PBC Traffic Engineering - Signal Loops

Stribling Way Pathways - From State Road 7 to the roundabout at Fairlane Farms on both sides

Asphalt pathways and overlay work

VOW ITB #202028 - Asphalt Milling expires 10/26/23

Pierson Road from 120th to South Shore Boulevard and on Ousley Farms Road from the C-51 canal to Bent Creek Road

Guardrail repair and maintenance

PBC Contract #2020052 - Guardrail expires 2/10/23

Concrete sidewalk repairs for various major thoroughfares and neighborhoods

Sidewalk repairs

VOW ITB #202112 - Minor Construction expires 5/10/24 PBC Contract #2020055 - Pathway & Minor Construction expires 11/16/23

Road base/shell rock maintenance and repairs for various roads throughout the Village.

Road base/shell rock maintenance and repairs

VOW ITB #202114 - Road Base expires 6/21/24

Surface Water:

 

Project Description Contracts

 

 

Amesbury Circle Subdivision, Chancellor Drive, Greenview Shores I, Paddock Park, Westhampton Subdivision, Aero Club Drive, Forest Hill Blvd and various areas throughout the Village, as needed.

Swale reconstruction around inlets and problem areas, and also prior to paving in order to follow the locations from the Roads Department resurfacing projects

VOW ITB #202101 - Public Works expires 1/11/24 VOW ITB #202111 - Sod expires 4/12/23

Canal desilting at C-2 to section C-24 and C-2 to section C-27A

Canal desilting to improve water conveyance

VOW ITB #202101 - Public Works expires 1/11/24

Greenview Shore I, Wiltshire Village, Lakeside Shores, and Montauk

Infrastructure drainage pipe, structure, culvert inspections and cleaning

VOW ITB #202030 - Drainage Infrastructure expires 10/12/23

Pump Station 4 Water Lube Conversion

Due to mechanical issues such as oil leaks, seal failure and lower bearing areas, the pumps are in need of repairs.  MWI Corporation is the custom engineer and fabricator of MWI pumps and a sole source provider. 

Sole Source - MWI Pumps

Pump Station 7 Trash Rake Reconditioning

The trash rake was refurbished in 2015 and is in need of maintenance and repairs.  The trash rake removes canal debris and vegetation from the protective bar screens on the upstream side of the pump station while the pumps are running.  Hydro Component Systems, LLC. is the original manufacturer.

Sole Source - Hydro Component Systems, LLC

 

Although the Village of Wellington and Palm Beach County contracts listed above are not set to expire at this time, and the sole source contracts/services are exempt from competition, the individual projects exceed $50,000, and require prior Council approval. 

 

Staff is seeking authorization to utilize the existing annual contracts and award sole source contracts summarized above for various FY 2022 Public Works projects that exceed $50,000. 

 

The total budgeted amount of all projects combined is $3,390,000.00. 

 

BUDGET AMENDMENT REQUIRED:                      NO 

 

PUBLIC HEARING:                      NO                      QUASI-JUDICIAL:   

 

FIRST READING:                                            SECOND READING:   

 

LEGAL SUFFICIENCY:                     YES  

 

FISCAL IMPACT:Funds are allocated in the FY 2022 Roads and Surface Water Divisions Operating Budgets, including carry forwards.

 

WELLINGTON FUNDAMENTAL:                      Responsive Government

 

RECOMMENDATION:  Authorization to utilize existing contracts and award sole source contracts for various FY 2022 Public Works Projects with a budgeted total amount of $3,390,000.00.