File #: 22-5114    Name: AUTHORIZATION TO AWARD A TASK ORDER TO FLORIDA DESIGN DRILLING CORPORATION FOR SURFICIAL AQUIFER WELL REHABILITATION SERVICES
Type: Purchasing/Contract
Body: Village Council
Agenda Date: 6/14/2022 Final action:
Title: ITEM: AUTHORIZATION TO AWARD A TASK ORDER TO FLORIDA DESIGN DRILLING CORPORATION FOR SURFICIAL AQUIFER WELL REHABILITATION SERVICES REQUEST: Authorization to award a task order to Florida Design Drilling Corporation for the rehabilitation of surficial aquifer wells R4, R8, and R10, in the amount of $480,612.
Attachments: 1. 1. Florida Design Drilling Corp Proposal, 2. 2. Rates, 3. 3. All Webbs Cancellation Letter, 4. 4. Council - 20-3971 - Wellfield Rehab
Date Action ByActionResultVoteMeeting DetailsVideo
No records to display.

…title

ITEM:                     AUTHORIZATION TO AWARD A TASK ORDER TO FLORIDA DESIGN DRILLING CORPORATION FOR SURFICIAL AQUIFER WELL REHABILITATION SERVICES

 

REQUEST:                     Authorization to award a task order to Florida Design Drilling Corporation for the rehabilitation of surficial aquifer wells R4, R8, and R10, in the amount of $480,612.

 

…body

EXPLANATION:                     On December 8, 2020, Council awarded two Contracts for Wellfield Rehabilitation and Maintenance to All Webb Enterprises, Inc. and Florida Design Drilling Corporation (ITB#202034).

 

On December 14, 2021, Council approved a task order to All Webbs Enterprises, Inc. for the rehabilitation of surficial aquifer wells R4, R8, and R10. On May 9, 2022, due to staffing shortages, All Webbs Enterprises, Inc. provided a cancellation notice. No work was performed under the task order.

 

Due to the inability of All Webbs Enterprises, Inc to complete the work, Staff is seeking authorization to award the project to Florida Design Drilling using a task order under the previously approved contract in the amount of $480,612, including $43,692 in owner controlled contingency and $39,720 in bonds and insurance.

 

BUDGET AMENDMENT REQUIRED:                     NO

 

PUBLIC HEARING:                     NO                      QUASI-JUDICIAL:                      

 

FIRST READING:                                            SECOND READING:                      

 

LEGAL SUFFICIENCY:                     YES

 

FISCAL IMPACT:                     Funds for this project are available in the Water Supply Improvements capital project (CUT22012).

 

WELLINGTON FUNDAMENTAL:                     Responsive Government

 

RECOMMENDATION:                     Authorization to award a task order to Florida Design Drilling Corporation for the rehabilitation of surficial aquifer wells R4, R8, and R10, in the amount of $480,612.