File #: 16-0457    Name: 1) AUTHORIZATION TO AWARD A CONTRACT FOR ELECTRICAL AND LIGHTING IMPROVEMENTS AT THE STRIBLING WAY AND FAIRLANE FARMS ROAD INTERSECTION; AND 2) APPROVAL OF RESOLUTION NO. R2016-69 AND ASSOCIATED BUDGET AMENDMENT #2016-065 TO SECURE THE FUNDS REQUIRED TO
Type: Purchasing/Contract
Body: Village Council
Agenda Date: 9/27/2016 Final action: 9/27/2016
Title: ITEM: 1) AUTHORIZATION TO AWARD A CONTRACT FOR ELECTRICAL AND LIGHTING IMPROVEMENTS AT THE STRIBLING WAY AND FAIRLANE FARMS ROAD INTERSECTION; AND 2) APPROVAL OF RESOLUTION NO. R2016-69 AND ASSOCIATED BUDGET AMENDMENT #2016-065 TO SECURE THE FUNDS REQUIRED TO COMPLETE THE PROJECT A RESOLUTION OF WELLINGTON, FLORIDA'S COUNCIL AMENDING THE ROAD IMPACT FEE FUND CAPITAL PROJECT BUDGETS FOR FISCAL YEAR 2015-2016 BY TRANSFERRING MONIES FROM THE 120TH AVENUE IMPROVEMENTS PROJECT TO THE FAIRLANE FARMS/STRIBLING WAY INTERSECTION IMPROVEMENT PROJECT; AND PROVIDING AN EFFECTIVE DATE. REQUEST: 1) Authorization to award a contract to Cerrito Electric for Electrical and Lighting Improvements at Stribling Way and Fairlane Farms Road in the amount of $79,068.95; and 2) Approval of Resolution No. R2016-69 and associated budget amendment #2016-065 in the amount of $50,000 to secure the funds required to complete the project.
Attachments: 1. 1. Resolution R2016-69 Stribling Roundabout Project, 2. 2. Bid Tabulation, 3. 3. Notice of Intent, 4. 4. Plans, 5. 5. Hyperlink to Bid Documents
...title
ITEM: 1) AUTHORIZATION TO AWARD A CONTRACT FOR ELECTRICAL AND LIGHTING IMPROVEMENTS AT THE STRIBLING WAY AND FAIRLANE FARMS ROAD INTERSECTION; AND 2) APPROVAL OF RESOLUTION NO. R2016-69 AND ASSOCIATED BUDGET AMENDMENT #2016-065 TO SECURE THE FUNDS REQUIRED TO COMPLETE THE PROJECT

A RESOLUTION OF WELLINGTON, FLORIDA'S COUNCIL AMENDING THE ROAD IMPACT FEE FUND CAPITAL PROJECT BUDGETS FOR FISCAL YEAR 2015-2016 BY TRANSFERRING MONIES FROM THE 120TH AVENUE IMPROVEMENTS PROJECT TO THE FAIRLANE FARMS/STRIBLING WAY INTERSECTION IMPROVEMENT PROJECT; AND PROVIDING AN EFFECTIVE DATE.

REQUEST: 1) Authorization to award a contract to Cerrito Electric for Electrical and Lighting Improvements at Stribling Way and Fairlane Farms Road in the amount of $79,068.95; and 2) Approval of Resolution No. R2016-69 and associated budget amendment #2016-065 in the amount of $50,000 to secure the funds required to complete the project.

...body
EXPLANATION: This project is part of the approved FY16 Capital Improvement Plan and provides much needed improvements to the Stribling Way and Fairlane Farms Road intersection. The intent of this bid is to enter into a construction contract for the electrical and lighting improvements for the Stribling Way and Fairlane Farms Road roundabout project. The roadway improvements phase of the project is currently under construction and is anticipated to be completed by the end of September. This phase of the project includes the procurement and installation of all necessary components required for a complete lighting system at Stribling Way and Fairlane Farms, as shown on the projects plans (attached).

On August 7, 2016, Wellington released ITB #025-16/DZ on Demandstar seeking qualified bidders to provide such service. The solicitation was also advertised in the Palm Beach Post and posted on Wellington's website. On August 31, 2016, five (5) proposals were received.


Vendor

Bid Amount
Local Preference Status
Cerrito Electric
$79,068....